Issue Date: April 18, 1997
Revision Date: November 6, 1997

ProTank, Inc.

LTP-5000 Line Tester

LINE TIGHTNESS TEST METHOD

Certification Leak rate of 0.1 gph with PD = 99.0% and PFA = 0.1%.
Leak Threshold 0.05 gph. 
A pipeline system should not be declared tight if the test result indicates a loss that equals or exceeds this threshold.
Applicability Gasoline, diesel, aviation fuel, fuel oil #4. 
Specification System tests fiberglass and steel pipelines. 
Tests are conducted at 150% operating pressure. 
Mechanical line leak detector must be removed from pipeline for duration of test.
Pipeline Capacity Maximum of 41 gallons.
Waiting Time None between delivery and testing. 
Minimum of 1 hour between dispensing and testing.
Test Period Minimum of 1 hour. 
Pipe deflection, vapor pockets, and large temperature differences may produce inconsistent readings. 
Testing to continue until stable conditions are present. 
Test data are acquired and recorded manually. 
Manual calculations are performed by operator on site.
Calibration Sensors must be calibrated in accordance with manufacturer's instructions before each test.

 

ProTank, Inc.

Evaluator: Midwest Research Institute

Manufacturer’s Previously Listed Contact Information is No Longer Valid.

Tel: (816) 753-7600

 

Date of Evaluation: 08/30/91

 

 | Home | Vendors: A - F | Vendors: G - M | Vendors: N - S | Vendors: T - Z | Method Index | Glossary |

Appearance on this list is not to be construed as an endorsement by any regulatory agency nor is it any guarantee of the performance of the method or equipment.
Equipment should be installed and operated in accordance with all applicable laws and regulations.  For full details, please refer to our expanded "DISCLAIMER" page.